150t/h – Granide Aggregate Production Process

150t/h – Granide Aggregate Production Flow Diagram

Note: Dotted portion in the flow diagram is the optional item that can be chosen according to the project actual situation.

150t/h – Granide Aggregate Production Equipment Configuration Table

Code Name Model Unit Quantity Power(kw) Total Power(kw) Output(t/h) Weight(kg) Remark
G1 Grizzly Feeder ZSW420×110 pc 1 15 15 120-280 5350  
P1 Jaw Crusher ASD-3625 pc 1 90 90 88-225 16500  
G2 Vibrating Feeder ZG200 pc 2 2×0.75 3 -200    
G3 Vibrating Feeder ZG100 pc 1 2×0.75 1.5 -100    
P2 Cone Crusher GPY100S pc 1 160 160 165-275 10300  
P3 Cone Crusher GPY100 pc 1 160 160 55-245 9000  
S1 Vibrating Screen 3YK1860 pc 1 37 37 100-650 10310  
XL1 Sand Washer XL762 pc 1 15 15 -75 5225 wet method
C1 Iron Separator   pc 1          
G4 Vibrating Feeder ZG100 pc 1 2×0.75 1.5 -100    
P4 Sand Making Machine PLS-850 pc 1 150-320 150-320 75-345 11520  
S2 Vibrating Screen 2YK1854 pc 1 30 30 70-550 7950  
XL2 Sand Washer XL914 pc 1 15 15 -100 6370 wet method
C2 Iron Separator   pc 1          

Note: The Equipment configuration listed in the table is for reference. The actual configuration is determined according to the feed granularity, finished product granularity or grading, production capacity, process condition, and topographical condition etc.