Normally, after the crushing machine being installed, some inspection should be done so as to make preparation for the latter test. Following are the inspection works for the crushing machine:
● Check whether oil pipe connect firmly, should be able to refill oil before test run.
● Check each part connection should be solid and reliable, and check carefully whether the other objects existed on the impeller, if have, should be ruled out in time.
● Check whether the motor wiring is correct, whether the voltage is normal(380V±5%).
● Before installing the belt, first start the motor, direction of rotation should be in line with brand direction of machine (i.e. seeing from the feeding opening, the impeller rotating in counterclockwise direction). If rotating in the opposite direction, should adjust the motor wiring to make rotation be in line with brand direction, not allowed to rotate in reverse direction.
● For double motor drive, the main shaft assembly and both sides motor should respective connect the main shaft assembly with the same number of V-belts, the tensioning force of both sides of V-belts should be adjusted and flat. Before checking and passed to production, first of all to do the no-load testing and load testing, confirmed by the test run and then handed over to the production department.