After repairing and maintaining of cone crusher, following is no-load test for 2-6 hours. If there is no problem, could proceed the next operation. What are the requirements of cone crusher? Let's have a look.
1. During commissioning, each interlock system should conform to the technical specification when stat and stop the machine.
2. The clockwise and anticlockwise rotation of movable taper could not exceed 15r/min.
3. The bevel gear should not be struck or have periodic noise.
4. Each lubrication point should be in normal condition without oil leakage.
5. Check whether the spring adjustment device and locking mechanism are adjusted according to the design requirement, and adjust the size of discharging opening with the requirements.